Interim Deliverables
Following key stages during the project lifecourse, PHENOTYPE will release deliverables which will provide an overview of interim results of the activities. These will be made public as close as possible to the planned submission date to the Commission (see below for document details).
Project milestones will be reported on following workshops in months 6 (June 2012), 24 (December 2013) and 42 (June 2015), as well as in the periodic reports planned for June 2013, December 2014 and December 2015.
Following key stages during the project lifecourse, PHENOTYPE will release deliverables which will provide an overview of interim results of the activities. These will be made public as close as possible to the planned submission date to the Commission (see below for document details).
Project milestones will be reported on following workshops in months 6 (June 2012), 24 (December 2013) and 42 (June 2015), as well as in the periodic reports planned for June 2013, December 2014 and December 2015.
Deliverable number |
Deliverable title |
Delivery date |
Status |
D1.1 | Management Handbook | Month 1 |
Completed |
D1.2 | Ethical Approvals | Month 13 |
Completed |
D1.3 | Consent Forms | Month 32 | Pending |
D2.1 | WP2 Study Protocol | Month 6 | Completed |
D2.2 | Workshop - Fieldwork Training Guide | Month 12 | Completed |
D2.3 | Database with newly collected data | Month 24 | Completed |
D2.4 | WP2 Report with preliminary results | Month 30 | Pending |
D2.5 | WP2 Final report | Month 36 | Pending |
D3.1 | WP3 Study Protocol | Month 6 | Completed |
D3.2 | Databases of natural health outcomes in Spain, The Netherlands, UK and Lithuania | Month 18 | Completed |
D3.3 | Statistical analysis results linking exposure and health outcomes | Month 32 | Pending |
D3.4 | WP3 Final report | Month 36 | Pending |
D4.1 | WP4 Study Protocol | Month 6 | Completed |
D4.2 | Database from first phase of studies collated for analysis | Month 20 | Completed |
D4.3 | Database from second phase of studies collated for analysis | Month 32 | Pending |
D4.4 | WP4 Final report | Month 36 | Pending |
D5.1 | WP5 Study Protocol | Month 6 | Completed |
D6.1 | Project Website | Month 6 | Completed |
D6.2 | Project Information Leaflet | Month 6 | Completed |
D6.3 | Dissemination Strategy | Month 6 | Completed |
D6.4 | Evaluation of Stakeholder Activities during year one of the PHENOTYPE project lifecycle | Month 12 | Completed |